Pengbian station () is a station on Line 14 of the Guangzhou Metro. It is located on the south side of Jianpeng Road, near the intersection with Pengxi Hualian Road on the north side of the planned Guangzhou Design City West Expansion Area, in the Jiahe Subdistrict of Baiyun District in Guangzhou. It opened on 29 September 2025.
Station layout
Station Floorings Pengbian Station has three floors, with a length of and a width of . The ground floor houses the station's exits, and is surrounded by Jianpeng Road, the , and nearby buildings. The first floor houses the station's equipment level, the second floor is the station concourse, and the third floor houses the Line 14 platform.
Pengbian station is the first Guangzhou Metro station built on a coal mining area, and is also the first metro station in mainland China to use UHPC prefabrication and assembly technology.
Concourse The station concourse features ticket vending machines and an intelligent customer service center. A dedicated elevator, multiple escalators, and stairs within the fare collection area provide convenient access to the platforms.
Platforms The station has an island platform located underground on the south side of Jianpeng Road. Toilets and a nursing room are located at the end of the platform towards .
Entrances/exits The station has 4 points of entry/exit. Among them, the C2 entrance/exit passage passes under the and several pipelines. It is the first entrance and exit passage in mainland China to be constructed using the shield method. Exit D is equipped with an elevator.
B: Jianpeng Road, Lianbian Pengxi Hualian Road, Yunqi Road C1: Jianpeng Road C2: Jianpeng Road, Lianbian Pengxi Dexing Road D: Jianpeng Road
Gallery
History When Phase 2 of Line 14 was approved, Pengbian station didn't exist in the plans at the time. Subsequently, a CPPCC member proposed the addition of a Pengbian station, which was adopted by the Guangzhou Municipal Government and eventually implemented.
Construction of the station started on 28 January 2019. In May 2023, the main structure of the station was topped out, making it the first station to be topped out in Phase 2 of Line 14. In April 2025, the station completed the “three rights” transfer. The station opened on 29 September 2025.