The Mandalgovi–Ulaanbaatar Transmission Line () or Ulaanbaatar–Mandalgovi Transmission Line () is a transmission line in Mongolia connecting Mandalgovi of Dundgovi Province and Ulaanbaatar.
History The groundbreaking of the construction of the transmission line was held on 21June2017. The transmission line was commissioned and handed over on 18October2019. The ceremony was attended by Minister of Energy Ts.Davaasuren, China Ambassador to Mongolia XingHaiming and Governor of Dundgovi Province O.Bat-Erdene.
Technical specifications The transmission line stretches for a length of 250km and includes two substations along its path. It carries AC electricity over two circuits of 330kV, Mongolia's highest voltage level for electricity transmission.
Finance The transmission line was constructed with US$5.95million funding from the Government of Mongolia and US$113.04million soft loan from Export–Import Bank of China.