The Darkhan Wastewater Treatment Plant is a wastewater treatment plant in Darkhan, Darkhan-Uul Province, Mongolia.

History The plant was originally constructed in 1965. In 1987, it underwent partial renovation. On 21December2017, the construction of the new plant commenced. The work also included the construction of the new 7.4km sewer pipe.

Technical specifications The plant has a daily processing capacity of 50,000m3 of water. Processed water is then discharged to the Kharaa River.

Finance In the latest recent renovation to the plant, the work was funded by the Asian Development Bank through a loan of US$18.5million. The remaining US$2million was funded by the Government of Mongolia.

See also Environmental issues in Mongolia

References

External links