Line 6 of Qingdao Metro () is an underground metro line in Qingdao. It's the first automatic operation metro line in Qingdao.
History Phase I Construction of phase I of line 6 started on 16 December 2019. Test run (without passengers) started on 12 September 2023. The phase I has started operation on 26 April 2024. It runs from Lingshan Bay to Hengyunshan Road. The section is 30.762 km in length with 21 stations.
Phase II Construction of phase II of Line 6, 13.85 km with 10 stations from Qingdao West railway station to Lingshan Bay, started on 2 July 2022.
Opening timeline SegmentCommencementLengthStation(s)NameLingshan Bay — Hengyunshan Road26 April 202421Phase 1Qingdao West railway station — Lingshan BayTBA10Phase 2
Stations Station name Connections Distance Location HuangdaoHongshulin -0Gangtou