Copper mining in Western Australia is relatively minor on a world scale, accounting for less than one percent of the world's production in 2021–22.
As of 2022, is the sixth most-valuable commodity in the state. It reached its highest-ever sales value in 2021–22 at almost A$2 billion and experienced a growth in production again after having experienced the lowest level in over a decade in the previous year.
Mining for copper in Western Australia is either carried out in designated copper mines, like the Golden Grove mine, the DeGrussa mine and the Jaguar mine and as a by-product, from the Nova and Savannah Mine, nickel mines, and the Boddington gold mine.
Copper production in Western Australia has fluctuated somewhat but nevertheless grown considerably. In 1990–91, the state produced 14,980 tonnes of copper, a figure that had grown ten-fold by 2010 and reached a peak of 211,186 in 2014. Similarly, the value of the industry has grown from A$23.9 million in 1990–91 to almost A$2 billion in 2021–22.Western Australian Mineral and Petroleum Statistics Digest 1998-99 Department of Mines, Industry Regulation and Safety, accessed: 28 March 2023
History
The origins of commercial copper mining in Western Australia date back to 1842, when a copper deposit was discovered at Wanerenooka, near the present-day Northampton. In the late 1890s and early 1900s there were small finds such as the Whim Creek copper mine in the Pilbara, Noting that the newspaper is incorrectly including the Pilbara location of Whim Creek in the Kimberley region and the Kimberley region.
Historical copper mining locations in Western Australia included many mines extracting other minerals at the same operation, where copper tonnage recovered was small. In the early twentieth century, most operations were small, and lasted a short duration. Northampton had copper mining as early as the 1860s, through to the 1890s.
Post-Second World War operations are the Elverdton Mine, near Ravensthorpe, which operated between 1956 and 1972, and the Thaduna Mine, near Wiluna, which was active intermittently from 1955 to 1971. In 1960, the leading copper mine in Western Australia was the Copper Hills Mine, located in the Pilbara and operational until 1963, with mining also carried out at Elverdton, Thaduna and the Kumarina Mine, the later deposit having been discovered before the First World War and mined intermittently until 1973.
By the late 1970s, copper was only mined as a by-product in nickel mines in Western Australia, with between 1,500 and 1,700 tonnes mined annually and a production value of around A$2 million.
Newer operations are the Teutonic Bore Mine, located near the Jaguar Mine, which operated from 1980 to 1985, owned by the Seltrust Mining Corporation. Teutonic Bore, upon opening, had a daily capacity to treat 1,000 tonnes of ore, and an annual capacity of 300,000 tonnes. Apart from copper, the mine also produced silver and zinc.
More prominent and longer-running was the Nifty copper mine, which operated from 1993 to 2019, while the Horseshoe Lights Mine, a combined gold and copper mine, operated from the late 1980s to 1994.
Historical production in Western Australia has been limited. In the early 1980s, Teutonic Bore was the only copper mine in the state, producing less than 3,500 tonnes of copper at a value of between A$3 and 4 million just before its closure.Western Australian Mineral and Petroleum Statistics Digest 1985-86 Department of Mines, Industry Regulation and Safety, accessed: 30 March 2023 By the early 1990s, copper mining in Western Australia produced around 12,000 tonnes annually at a value of A$20 million from three locations, the Golden Grove and Telfer Mines and Kambalda.Western Australian Mineral and Petroleum Statistics Digest 1991-92 Department of Mines, Industry Regulation and Safety, accessed: 30 March 2023
Current mining operations
The following companies operated copper mines in Western Australia in 2022–23, according to the Department of Mines, Industry Regulation and Safety. To qualify for the department's official list of principal mining projects an operation has to either had mineral sales valued at more than $5 million, or, for operations where such figures are not reported, had a minimum of 50 employees: MineOwnerLocationProduction(tonnes)PeriodSource Boddington gold mine Newmont Shire of Boddington 44,450 2023 DeGrussa Mine Sandfire Resources Shire of Meekatharra 27,791 2022–23 Golden Grove mine 29Metals Limited Shire of Yalgoo 18,100 2023 Jaguar Mine Aeris Resources Shire of Leonora 3,100 2022–23 Nova Operations IGO Limited Shire of Dundas 10,266 2022–23 Savannah Mine Panoramic Resources Shire of Halls Creek 3,129 2022–23 Telfer mine Newmont Shire of East Pilbara 17,000 2022–23
The Boddington gold mine also produced 745,000 ounces of gold in 2023 The DeGrussa Mine also produced 19,122 ounces of gold in 2022–23. Mining at DeGrussa ceased in October 2022, with the plant continuing to process existing stockpiles only The Golden Grove mine also produced 14,000 ounces of gold, 775,000 ounces of silver, 1,170 tonnes of lead and 51,500 tonnes of zinc in 2023 The Jaguar Mine also produced 22,500 tonnes of zinc, 718,000 ounces of silver and 3,000 ounces of gold in 2022–23. The mine was subsequently placed in care and maintenance in September 2023. The Nova Operations also produced 22,915 tonnes of nickel and 803 of cobalt in 2022–23 The Savannah Mine also produced 5,402 tonnes of nickel and 368 of cobalt in 2022–23 The Telfer mine also produced 349,000 ounces of gold and 208,000 ounces of silver in 2022–23
Export In 2021–22, over seventy percent of the state's copper concentrate production went to South Korea (27 percent), the Philippines (24 percent) and Japan (22 percent). Germany and Finland followed next in this list with nine and five percent each respectively.
Environmental issues In 2019, the owners of the Whim Creek copper mine were handed an Environmental Protection Notice by the Department of Water and Environmental Regulation because of seepage of heavy metals from the mine into the Balla Balla River, considered a serious pollution risk. While in care and maintenance and with no active mining, Black Rock Minerals re-processed existing stockpiles through a small process plant and heap leach. Copper levels of 3.5 milligrams per litre were recorded in the local drinking water, well above the permitted level of 0.002 milligrams per litre. The small scale re-processing at Whim Creek eventually ceased in October 2019.
Statistics
Annual statistics for the Western Australian copper mining industry. Figures are for financial year, which, in Australia, runs from 1 July to 30 June. Employment figures are for the base metal mining industry overall:Western Australian Mineral and Petroleum Statistics Digest 2022-23 Department of Mines, Industry Regulation and Safety, accessed: 1 June 2024Western Australian Mineral and Petroleum Statistics Digest 2021-22 Department of Mines, Industry Regulation and Safety, accessed: 28 March 2023Western Australian Mineral and Petroleum Statistics Digest 2020-21 Department of Mines, Industry Regulation and Safety, accessed: 25 March 2022Western Australian Mineral and Petroleum Statistics Digest 2019-20 Department of Mines, Industry Regulation and Safety, accessed: 31 March 2022Western Australian Mineral and Petroleum Statistics Digest 2012-13 Department of Mines, Industry Regulation and Safety, accessed: 12 March 2023Western Australian Mineral and Petroleum Statistics Digest 2002-03 Department of Mines, Industry Regulation and Safety, accessed: 31 March 2023Western Australian Mineral and Petroleum Statistics Digest 1999-00 Department of Mines, Industry Regulation and Safety, accessed: 31 March 2023 Subject 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 Production (tonnes/annum) 14,980 12,000 12,002 22,920 32,460 29,200 23,690 27,730 29,430 24,440 Production value (A$ million) 23.92 20.35 17.44 27.44 40.26 76.54 65.42 58.98 61.12 43.71
Subject 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Production (tonnes/annum) 30,730 42,620 53,500 59,410 53,290 61,930 81,200 115,980 124,530 127,330 Production value (A$ million) 64.62 111.12 122.57 138.57 155.82 243.73 559.85 1,052.5 1,080.6 654.34 Employees 1,331 1,301 1,295 1,100 888 670 912 2,241 2,242 1,456
Subject 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Production (tonnes/annum) 149,810 148,760 155,080 198,610 211,186 184,495 190,275 170,730 174,074 162,483 Production value (A$ million) 1,156.7 1,290.1 1,165.5 1,441.2 1,559.6 1,283.1 1,181.3 1,240.5 1,347.8 1,321.6 Employees 1,926 2,317 2,907 2,882 2,649 2,531 2,358 2,239 2,535 2,626
Subject 2020 2021 2022 2023 Production (tonnes/annum) 169,888 145,853 153,321 119,128 Production value (A$ billion) 1,386.8 1,485.1 1,963.4 1,401 Employees (Full time) 2,075 1,894 2,072 1,994 Employees (all personnel on site) 2,636 2,319 2,471
Notes
Full time employees only. Up until 2022, the Western Australian Mineral and Petroleum Statistics Digest listed a combined figure of both full time employees and on-site personnel but the latter was not included in the 2022–23 edition, which only listed full time employees.
References