+Offshore Windfarm capacity in GW This is a list of offshore wind farms within the national maritime boundaries of the United Kingdom.

In July 2026 the nameplate capacity of offshore wind farms in operation was approximately 16.6 GW, with a further 10.4 GW under construction and 5.4 GW in pre-construction. Contracts for difference for a further 6.7 GW have been awarded by the UK Government. A further 36.8 GW are in early planning stages.

If all proposed wind farms are developed, by the 2030s, the United Kingdom's nameplate capacity is expected to reach approximately 76 GW.

A total of 5.9 GW of proposed OWFs has been cancelled.

__TOC__

Operational offshore wind farms In July 2025, there were offshore wind farms consisting of 2,809 turbines with a combined capacity of 16,035 megawatts. Strike price is the fixed rate offered under the Contracts for Difference subsidy scheme, based on £/MWh at 2012 prices. Older projects were under the Renewables Obligation schemes, and did not get a set price.

Name Country Location Capacity(MW)No. Turbinemanufacturer(s)Turbine model(s) Projectcommissioning year Strikeprice Buildcost Capacityfactor Depthrange (m) km toshore Owner Refs. Barrow England 90 30Vestas V90-3.0 MW £123m 35.9% 15–20 7 Ørsted Barrow Offshore Wind FarmBarrow Offshore Wind Farm (UK) 4C . Retrieved: 9 February 2015. BeatriceScotland 10 2REpower 5M £35m 20% 45 23 SSE, Talisman Energy Beatrice offshore wind farm (United Kingdom) 4C . Retrieved: 27 October 2010. Beatrice extensionScotland 588 84Siemens Gamesa SWT-7.0-154 140 £2,600m 45 23 SSE Talisman Energy Beatrice extension Retrieved: 27 October 2010.Royal Opening for Scotland's Largest Offshore Wind Farm Retrieved: 17 August 2019.Blyth Offshore DemonstratorEngland 41.5 5Vestas V164-8 MW 50-606.5EDF Renewables Burbo BankEngland 90 25Siemens SWT-3.6-107 £90m 32–35% 0–6 7 Ørsted Burbo BankBurbo Bank Offshore Wind Farm (United Kingdom) 4C . Retrieved: 7 November 2010. Burbo Bank ExtensionEngland 258 32Vestas V164 8.0 MW 6–13 Ørsted DudgeonEngland 402 67Siemens SWT-6.0–154 £1,500m 48% Equinor, Statkraft Dudgeon Wind Farm project pageDudgeon 4C . East Anglia One England 714 102Siemens SWT-7.0-154 119.8943 Crown Estate - Offshore Wind Operational Report Retrieved: 17 August 2019. European Offshore Wind Deployment CentreScotland 93 11Vestas Vestas V164 8 MW 32 3 European Offshore Wind Deployment Centre GalloperEngland35356SiemensSWT-6.0-15427-3627RWE Greater GabbardEngland 504 140Siemens SWT-3.6-107 £1,500m 42.2% 20–32 23 SSE Renewables Gunfleet Sands 1 & 2England 172 48Siemens SWT-3.6-107 £300m 36.6% 2–15 7 Ørsted Gunfleet SandsGunfleet Sands offshore wind farm (United Kingdom) 4C . Retrieved: 27 October 2010. Gunfleet Sands 3 – Demonstration ProjectEngland 12 2Siemens SWT-6.0-120 £51m 31.1% 5–12 8 Ørsted Gunfleet Sands demonstration project Gwynt y MôrWales 576 160Siemens SWT-3.6-107 >£2,000m 31.7% 20 17 RWE Npower, Stadtwerke München, GIB, Siemens Gwynt y Môr Hornsea One England 1218 174Siemens SWT-7.0-154 140Ørsted, Global Infrastructure PartnersHornsea TwoEngland 1386 165SiemensSG 8.0-167 DD 57.5025-30120Ørsted, Global Infrastructure PartnersHornsea Two Offshore Wind Farm Retrieved: 17 Aug 2019. Humber GatewayEngland 219 73Vestas V112 3.0 MW £736m 41.1% 15 10 E.ON Humber Gateway Hywind ScotlandScotland 30 5Siemens SWT-6.0-154 NOK2 billion(£152m) 54% 95–120 25 Equinor, Masdar Kentish FlatsEngland 140 30Vestas V90-3.0 MWand V112-3.3MW £121.5m 31.3%,42.9% 3–5 10 Vattenfall Kentish FlatsKentish Flats offshore wind farm (United Kingdom) 4C . Retrieved: 27 October 2010.KincardineScotland49.56VestasV164-9.5 MWand V80-2 MW 60–8015Principle Power, Flotation Energy, Cobra Wind LincsEngland 270 75Siemens SWT-3.6-120 £1,000m 42% 10–15 8 Centrica, Siemens, Ørsted Lincs Lincs Offshore Wind Farm (United Kingdom) 4C . Retrieved: January 2015. London ArrayEngland 630 175Siemens SWT-3.6-107 £1,800m 41.1% 0–25 20 Ørsted, E.ON UK Renewables, Masdar London Array Lynn and Inner DowsingEngland 194 54Siemens SWP-3.6-107 £300m 34.9% 6–11 5 Centrica 50% TCW 50% Lynn and Inner Dowsing Lynn Inner Dowsing offshore wind farm (United Kingdom) 4C . Retrieved: 25 October 2010. MethilScotland 7 1Samsung 7 MW 5 0.05 Samsung, 2-B Energy Energy Park Fife (Methil)Moray EastScotland950100VestasV164-9.5 MW 57.50 25–30 120Ocean Winds4C Offshore - Moray East Moray West Scotland 88260 Siemens Gamesa SG 14-222 DD 37.35 & 54.23 £2,500m 35–54 22.5 Ocean Wind Neart Na GaoitheScotland45054SiemensGamesa SG 8.0-167 DDJuly 2025114.3920EDF R / ESB North HoyleWales 60 30Vestas V80-2 MW £80m 31.5% 5–12 7 Greencoat UK Wind North HoyleNorth Hoyle Offshore Wind Farm (United Kingdom) 4C . Retrieved: 7 November 2010. OrmondeEngland 150 30REpower 5 MW £552m 39.5% 17–22 9.5 Vattenfall Ormonde, Irish SeaOrmonde (UK) offshore wind farm 4C . Retrieved: 9 February 2015. Race BankEngland 580 91Siemens SWT-6.0-154 Ørsted Race Bank Wind Farm project page RampionEngland 400 116Vestas V112-3.45 MW £1,300m 13 E.ON Rampion Wind Farm project pageRampion 4C . Rhyl FlatsWales 90 25Siemens SWT-3.6-107 £198m 32.9% 4–15 8 Npower (UK) (RWE) Rhyl FlatsRhyl Flats Offshore Wind Farm (United Kingdom) 4C . Retrieved: 7 November 2010. Robin RiggScotland 180 60Vestas V90-3.0 MW £396m 35.1% 0–12 11 E.ON Robin RiggRobin Rigg Offshore Wind Farm (United Kingdom) 4C . Retrieved: 7 November 2010. Scroby SandsEngland 60 30Vestas V80-2 MW £75.5m 30.7% 0–8 2.5 E.ON Scroby SandsScroby Sands offshore wind farm (United Kingdom) 4C . Retrieved: 27 October 2010.Seagreen Phase 1Scotland1400114VestasV164-10.0 MW 41.61£3,000mUp to 59SSE Renewables, TotalEnergies Sheringham ShoalEngland 317 88Siemens SWT-3.6-107 £1,100m 40.7% 12–24 17 Equinor 50%Statkraft 50% Statkraft – Sheringham Shoal TeessideEngland 62 27Siemens SWT-2.3-93 £200m 34.8% 7–15 1.5 EDF-EN Teesside offshore wind farm (United Kingdom) 4C . Retrieved: 11 February 2015. ThanetEngland 300 100Vestas V90-3.0 MW £900m 32.8% 20–25 11 Vattenfall ThanetThanet Offshore Wind Farm (United Kingdom) 4C . Retrieved: 24 September 2010.Triton KnollEngland 857 90Vestasv164-9.5 MW 74.7533RWE WalneyEngland 367 102Siemens SWT-3.6-107 £630m 40.5%,43.8% 19–30 14 Ørsted, SSE, OPW Walney Offshore WindfarmWalney 1, Walney 2 4C . Retrieved: 9 February 2015. Walney ExtensionEngland 659 87Siemens Vestas SWT-7.0-154 MHI V164-8.25 150.00 Ørsted Walney Extension Wind Farm project pageWalney Extension 4C . Westermost RoughEngland 210 35Siemens SWT-6.0-154 £370m 42.9% 15 10 Ørsted, Marubeni, GIB Westermost Rough West of Duddon SandsEngland 389 108Siemens SWT-3.6-120 £1,600m 44.2% 17–24 15 Ørsted, Scottish Power West of Duddon SandsWest of Duddon Sands (UK) offshore wind farm 4C . Retrieved: 9 February 2015. +NotesAbbreviationExplanationCap.The rated nameplate capacity of the wind farm.No.The number of wind turbines.ModelThe model of wind turbine.CostThe total capital cost of the project up to commissioning.Cap. fac.The average capacity factor, i.e. the average power generated by the wind farm, as a percentage of its nameplate capacity.Km to shoreThe average distance of the wind farm to shore, or (where available) the distance from the in-farm transformer/substation to the shore.Depth range (m)The range of minimum to maximum depths of water in which the wind farm is sited.RefsThe source references for the information. The [w ...] footnotes link to each wind farm's own home page.

Map of the UK offshore wind farms

Wind farms under construction These are offshore wind farms currently under construction (offshore), with a combined capacity in February 2026 of 10,392 MW. Strike price is based on £/MWh at 2012 prices.

Name Country Location Cap. (MW) No.Model Project commissioning Strike price Depthrange (m) Km toshore Owner Refs. Sofia Offshore Wind Farm England 1400 100Siemens Gamesa SG 14-222 DD 2026 39.65 195 RWEDogger Bank AEngland 1235 95GE-Haliade X 13 MW 2026 39.65 131 SSE Renewables, EquinorDogger Bank BEngland123595GE-Haliade X 13 MW202741.61SSE Renewables, EquinorDogger Bank CEngland121887GE-Haliade X 14 MW202741.61SSE Renewables, EquinorEast Anglia ThreeEnglandTM097462137295Siemens Gamesa SG 14-236 DD202637.35 (159 MW for AR6 @ 54.23)Iberdrola Inch Cape Scotland NT394753108072 Vestas V236-15 2027 37.35 (251 MW for AR6 @ 54.23)Inch Cape OffshoreHornsea ThreeEnglandTG2100342852197Siemens Gamesa SG 14-236 DD202837.35 (1080 MW for AR6 @ 54.23)160ØrstedHornsea Three

Pre-construction wind farms These are wind farms that have started onshore construction and have been awarded contracts under the UK Government's Contracts for Difference Round 4 (2022), Round 6 (2024) for East Anglia and Round 7 (2026) for Vanguard. Total capacity of 5,433 MW. Strike price is based on £/MWh at 2012 prices for Norfolk Boreas and £/MWh at 2024 prices for Vanguard.

Name Country Location Cap. (MW) No. Model Projectcommissioning Strike price Depthrange (m) Km toshore Owner Refs.Norfolk BoreasEngland1380Vestas202737.3572RWENorfolk BoreasEast Anglia TwoEngland96364Siemens Gamesa SG 14-236 DD202858.8733IberdrolaNorfolk Vanguard WestEngland154592Vestas V236-152028/2991.2030-46RWENorfolk Vanguard EastEngland154592Vestas V236-152028/2991.2030-41RWENorfolk Vanguard

Proposed wind farms - Contracts for Difference Round 6 These are wind farms proposed under the Round 6 (2024) CFD auction, with a combined capacity of 400 MW. Strike price is based on £/MWh at 2012 prices. Name Country Location Cap. (MW) No. Model Projectcommissioning Strike price Depthrange (m) Km toshore Owner Notes Refs.Green Volt OWFScotlandNJ8304454002029139.93Green Volt Note: this table does not include OWFs that were awarded contracts in AR4, and have now received a new contract as a result of permitted reduction in AR6.

Proposed wind farms - Contracts for Difference Round 7 These are wind farms proposed under the Round 7 (2025/6) CFD auction, with a combined capacity of 5,347.5 MW. Strike price is based on £/MWh at 2024 prices. Name Country Location Cap. (MW) No. Model Projectcommissioning Strike price Depthrange (m) Km toshore Owner Notes Refs.Awel y MôrWalesSJ0157357752030/3191.20Awel y Môr OWF LtdBerwick Bank Phase BScotlandNT30774513802030/3189.49Berwick Bank B LtdOnly Phase BDogger Bank SEEnglandTA0443491500Construction 2027 Commissioning 2030/3191.20RWE Renewables UKPlanning permission received 14 May 2026Dogger Bank SWEnglandTA0443491500Construction 2027 Commissioning 2030/3191.20RWE Renewables UKPlanning permission received 14 May 2026ErebusWalesSM9350141002029/30216.49Blue Gem Wind LtdPentland Floating OWFScotlandNC98166692.52029/30216.49Highland Wind Ltd

Proposed wind farms - early planning These are wind farms that are in an exploratory phase and have not yet secured a Contract for Difference at auction.

Total capacities: England: 10,060 MW - Scotland: 26,226 MW Name Country Location Cap. (MW) No. Model/ capacity Technology Projectcommissioning Option price Depthrange (m) Km toshore Owner Notes Refs.East Anglia One NorthEngland 800up to 67Fixed 37.7 IberdrolaAwaiting CFD Rampion 2 ExtensionEngland 120090FixedConstruction 2027 Commissioning 2030 RWE, Macquarie, EnbridgeApril 2025: granted development consent by Government. West Sussex County Council Rampion Wind Farm Extension project pageFive EstuariesEnglandAdjacent to Galloper Wind Farm1080up to 79FixedConstruction 2027 Commissioning 2030 RWEDCO granted - Dec 2025North FallsEnglandAdjacent to Greater Gabbard wind farm504 (up to 1000)57FixedConstruction 2027