Pilmaiquén Hydroelectric Plant is a series of hydroelectric power stations and projects owned by Statkraft, using water from Pilmaiquén River in Los Ríos Region, Chile.

Rucatayo The Rucatayo plant produces of electricity. The plant was built by ENDESA between 1944 and 1959 was owned by Pilmaiquén S.A.Electricity generation capacity of Chile as of July 2007 by Comisión Nacional de Energía until 2015, when Statkraft bought it, along with the development rights to Osorno and Los Lagos. Rucatayo delivers around 304 GWh per year.

Los Lagos The Los Lagos project was planned at 50.8 MW power, delivering around 310 GWh per year. It was modified to 51.6 MW power, but reduced to 260 GWh energy per year, starting in late 2022.

Osorno The Osorno project has 54.3 MW power, delivering around 343 GWh per year. No decision has been made about starting the project.